Planning fallacy
We tend to think our own tasks will take less time than they do, even when we know similar tasks ran late before. We picture the plan and forget our track record.
Example
In one study, students guessed their thesis would take about 34 days; it took about 56, and fewer than a third finished by their own best guess.
When to use it
When estimating design work, check how long similar past projects really took and tie that to this one: just remembering them didn't help in the study. Someone outside the project may give a more cautious estimate, though more cautious isn't the same as more accurate.
Watch out
In these student studies, linking past tasks made estimates less optimistic, but no more accurate overall.
The evidence 5 sourced claims
Every sentence on this card traces back to one of these claims, each linked to its source. How we research
The planning fallacy is the tendency to believe confidently that one's own project will go as planned, even while knowing that most similar projects have run late (term from Kahneman & Tversky 1979).
Students writing an honours thesis predicted about 34 days on average but took about 56; fewer than a third finished by their own best guess, and even their worst-case guesses (about 49 days) were on average too short.
When predicting, people focused overwhelmingly on their plans for the current task and rarely thought about how long past tasks took.
Simply reminding people of past experiences did not reduce the bias; it went away only when people had to connect relevant past experiences to their current prediction.
Observers predicting someone else's completion time were more cautious than the person themselves and more likely to consider that person's past.